Projeler - Trabzon Cement Grinding Plant (85 T/H)

Projeler - Trabzon Cement Grinding Plant (85 T/H)

projects Description
Project :

Trabzon Cement Factory Grinding Plant With Capacity 85 Tons/HR

Client : Aşkale Cement Industry Inc.
Contract Date : 04.09.2006
Completion Date : The project was completed on 22.05.2007.
Duration : 7Months
Status : Sub-Contractor
Percentage Of Participation : 100 %
General Description Of The Project : The project has been performed on a turnkey basis.
Detailed Description Of The Project :
  • System design,
  • Civil works,
  • Conveying systems,
  • Manufacturing and erection of filters and steel structures,
  • Dosing weight feeders,
  • Electrical & automation works,
  • Start up and commissioning.
Liquidated Damages : None
Main Sub- Suppliers : None