| Project | : |
Trabzon Cement Factory Grinding Plant With Capacity 85 Tons/HR |
| Client | : | Aşkale Cement Industry Inc. |
| Contract Date | : | 04.09.2006 |
| Completion Date | : | The project was completed on 22.05.2007. |
| Duration | : | 7Months |
| Status | : | Sub-Contractor |
| Percentage Of Participation | : | 100 % |
| General Description Of The Project | : | The project has been performed on a turnkey basis. |
| Detailed Description Of The Project | : |
|
| Liquidated Damages | : | None |
| Main Sub- Suppliers | : | None |
projects Description
- 0
- 6 June 2022
- Cement Industry