Isdemir Ore Dressing Facility

 

Project  : İSDEMİR Modernization Investment Programme  Ore Dressing Facility in İskenderun
Client : İSDEMİR – İskenderun Iron & Steel Co.
Consultant  : ERENCO – Erdemir Engineering Management & Consulting Services Inc.
Contract Date
Commencement Date

:

:

05.03.2007

08.03.2007

Duration : 450 Day         
Status :

Main Contractor

Percentage Of Participation

:

100 %

 

General Description Of The Project :

Scope of the project includes modernization, engineering, production, construction and erection of ore preparation system, blending and manipulation of raw material.

 

Detailed Description Of The Project

 

 

 

:

Sections of Factory:

  • Conveyor : 500 m
  • Stacker : Erection          
  • Reclaimer : Erection

Completed works:

  • Excavation : 000 m3
  • Piling :   000 m
  • Concrete :   000 m3
  • Steel Structure :     800 tons
  • Electrical System ( Complete )
  • Automation System
  • Instrumentation
Main Subcontractor :

SIEMENS