Boğazlıyan Sugar Factory    (10000 T/D)

 

Project  : Boğazlıyan Sugar Factory (10000 T/D)
Client : Kayseri Sugar Factory Co.
Contract Date :

December 2004

Commencement Date : 01 July 2005
Completion Date :

First sugar production is realized on 03.Dec.2006 and Provisional acceptance is achieved on 06 November 2007

Status : Consortium
Percentage Of Participation :

Project is completed by Consortium of FIVES CAIL-MAGUIN-(OYAK-EKON-PROKON JV) FIVES CAIL-MAGUIN are suppliers of know-how and some parts of equipments. Participation Percentage of OYAK-EKON-PROKON JV is as mentioned below,

  •  OYAK            : 45 %
  •  EKON            : 45 %
  •  PROKON       : 10 %
General Description Of The Project :

Turnkey Construction of Sugar Factory having 10,000 (ten thousand) Tons/ Day Actual Beet Processing Capacity.

 

Detailed Description Of The Project

:
  • Beet Yard : 52.500 m²
  • Beet Conveyor : 650 m
  • Beet Washing Plant
  • Main Process Building : 130 m x 30 m x 21 m
  • Diffusion Tower and Cassette Mixer
  • Pulp Conveyor
  • Juice Purification
  • Evaporation
  • Crystallization
  • Sugar Drying Building and equipment
  • Sugar Conveying
  • Horizontal Sugar Silo Building : 60.000 TON
  • Bagged Sugar Storage Building : 20.000 TON
  • Milk of Lime Production Building : 500 m³
  • Cooling Tower
  • Boiler Building : 2 x 75 T/h
                           20 T/Hour + 10 T/Hour
  • Turbine Building : 2 x 7.5 MW
  • Piping : 45.000 m (various)
  • Molasses Tanks : 2 x 11.000 TON
  • Fuel Oil Tank :         000 TON
  • Waste Water Treatment Plant
  • Administration and Social Buildings

 Completed works;

 

  • Excavation : 350.000 m³
  • Concrete :   000 m³
  • Steel Structure :     200 TON
  • Electrical System (Complete)
  • Automation System
  • Instrumentation